Scaffold Erecting and Dismantling Procedure

Scaffold Erecting and Dismantling Procedure

  • Fit Castors to base frame
  • Attached horizontal brace (whitebrace)to vertical tube of the base frame.Ensure casters are locked. The frame is nowSelf-Supporting
  • Attach the Spare end of the brace to the other base frame
  • Attach two diagonal braces {blackbraces) to the base unit as shown. Leval the unit using adjustable legs, the base is now complete.
  • For the next stage-insert next riser frames on to spigots of the pattern of Diagonal Braces(a new diagonal brace starts where the one beneath finishes and rises two transoms) this pattern carries on up to the working top deck
  • Attach guardrail frame sat each end above the top working plattform
  • Attach guadrail frame sat each end above the top working platform
  • Attach 1 to 1 diagonal brace (black from one frame another frame).
  • Two horizontal braces are clipped on to the top transoms In a horizontal plane (creating a 1m handrail) with a further two horizontals clipped to the next transome down (creating a5OO mm mid rail).
  • Fit toe boards
  • All Single width & double width scaffold must be fitted with outriggers(or external all ties)above 4 mtr
  • Check all four wheels are locked
  • Before using the tower, ensure the scaffold is checked and built correctly
  • Ensure the safety compliance sticker, hazard reduction sticker and safe working load guide are followed at all times
  • Dismantling procedure id is reverse methods to that of the erection process (Follow 14 to 1)
Call Now Button